New Elementary School: projected timeline

Below are some tentative timelines related to bond construction projects:

  • April-May 2019- Bids will be awarded for the construction of the new elementary school and some summer remodel projects.
  • June 2019- Construction begins for new elementary school and remodel projects.
  • August-September 2019- Completion of summer remodel projects.
  • Fall-Winter 2019-2020- Principal selected for new school.
  • Fall-Winter 2019-2020- Process for changing elementary school attendance boundaries finalized.
  • Winter-Spring 2020- Elementary attendance boundaries revision completed.
  • Spring 2020- New school named.
  • June-August 2020- Second round of remodel projects are completed.
  • August 2020- Construction of new school completed.  District moves into new school.
  • September 2020- New elementary school opens for students.
  • June-August 2021- Third round of remodel projects are completed.

Once again, thank you very much for your support of the Post Falls School District.